A complete fire station with very detailed secondary items attached to the Structural Frame. The station houses a gymnasium, offices, classrooms, truck bays, and multi-purpose areas.
This project is currently under Engineering & Approval review.
Deanwood Community Center has been posted. Please see "Projects" page. This steel erection on this project is nearing completion. The scissor trusses in the pool area were the last major area to be erected. Erection and Detailing were sequenced into 4 areas to facilitate timely deliveries, and jobsite requirements.